Amenity Water Limited Logo

Flood Defence Outfall Refurbishment

This project was to re-furbish an outfall on the River Stour and improve the access arrangements to it for future maintenance.

  • Img 1202
    The long reach excavator is delivered to the narrow lane leading to the site.
  • Img 1220
    With the pumping chamber beneath sufficiently protected the excavator is positioned in place behind the flood wall.
  • Img 1215
    This enables it to reach sufficiently into the river to construct the temporary dam and work on the outfall.
  • Dscn1373
    With the temporary dam in place the formwork is constructed and reinforcing installed ready for the new concrete.
  • Dscn1384
    The new concrete frontage of the outfall taken from below water level!
  • Dscn1408
    The bin store with gate leading to the steps over the flood wall.
  • Dscn1404
    The refurbished outfall looking downstream showing the lower steps and new fencing.
  • Img 1202
  • Img 1220
  • Img 1215
  • Dscn1373
  • Dscn1384
  • Dscn1408
  • Dscn1404

The structure of the existing outfall had been compromised through age and freeze thaw weathering and so a new layer of reinforced concrete was to be cast over the existing structure.

Two new sets of steps were incorporated into the design to enable safer access to the outfall for future maintenance and the residents of the adjacent houses were to be provided with a new fenced area to store their bins.

The access was very tight down a narrow cul de sac lane to some houses. A long reach excavator was required to reach over the flood defence wall and work on the structure. In order to carry out the works this machine had to sit on the pumping chamber that fed the outfall and so a temporary works to design protect the chamber and spread the load of the machine was devised.

A temporary dam was installed in the river to keep the working area dry and a pump was set up to deal with the seepage through it.

The pipes from the pumping chamber that discharge onto the outfall were extended over the temporary dam to keep the working area dry in case of rain during the construction works.

The existing structure was cleaned and prepared to receive the new concrete before the reinforcing was installed.

The formwork was constructed around the existing structure and the new concrete was poured.

Once the concrete had cured sufficiently the formwork and temporary dam could be removed.

The two sets of steps were then installed, the new bin store was constructed and some other fencing to deter public access was erected.

CLIENT DETAILS

The Environment Agency

Rio House, Bristol

LOCATION

Blandford Forum, Dorset

MATERIALS USED
  • Concrete and reinforcing steel
  • Galvanised fencing wire and staples
  • Interlocking steel sheet piles