Amenity Water Limited Logo

Rock Ramp Perturbation Fish Pass

This project was to construct a rock ramp perturbation fish pass at the site of twin weirs enabling migratory fish to access the upper River Ouse once again.

  • Dscf6905
    The upstream temporary dam and pipework from two of the pumps.
  • Dscf6907
    The downstream temporary dam and a diesel pump dealing with the seepage through it.
  • Dscf6911
    The formwork is constructed around the base of the boulders prior to the final concrete pour to secure them in place.
  • Dscf6917
    The boulders in place before final concreting looking upstream.
  • Dscf7201
    The commissioned fish pass.
  • Dscf6905
  • Dscf6907
  • Dscf6911
  • Dscf6917
  • Dscf7201

Two temporary dams were installed to divert the entire flow of the river over the right bank weir leaving the left channel dry for the construction of the fish pass.

Two diesel and two electric submersible pumps were used running 24 hours to keep the working area dry for the duration of the works.

The channel was excavated in order to construct the base for the fish pass. Once this had cured the boulders were imported and placed out before being set in concrete.

The upstream and downstream ends of the fish pass were protected with a smaller grade of rock.

CLIENT DETAILS

The Environment Agency

Guildbourne House, Worthing

LOCATION

Sharpsbridge, Uckfield, East Sussex

MATERIALS USED
  • Armorloc interlocking concrete blocks
  • Granite rip rap stone
  • Imported crushed stone
  • Woven geotextile